gantt
title OA Country Report Production Schedule
dateFormat YYYY-MM-DD
axisFormat %b %d
%% Sections for each phase
section Phase 1: Planning & Data Collection
Review and Analysis :milestone, m1, 2025-06-09, 0d
Literature & Data Gathering :active, a1, after m1, 4d
Data Analysis :a2, after a1, 6d
Finalize Data :milestone, m2, 2025-06-20, 0d
section Phase 2: Report Drafting
Report Writing :crit, b1, 2025-06-29, 2d
Results Section :b2, after b1, 3d
Water Carbon Chemistry :b3, after b2, 3d
First Complete Draft :milestone, m3, 2025-07-04, 0d
section Phase 3: Review & Finalization
Internal Review :crit, c1, 2025-07-04, 4d
Incorporate Revisions :c2, after c1, 3d
Design & Layout :c3, after c2, 2d
Quality Assurance :crit, c4, 2025-07-20, 8d
Final Delivery :milestone, m4, 2025-07-30, 0d